Project Management  Series-10

Quiz Project Management  Series-10 quiz you are applying for a job / interview / Competitive Exams RBB, SSC, MBA, B.Com, BBA Enterence exams Solving quiz you will prepare yourself..

1
Created on By 52fd849a905aedf0249df9e69d61b55a?s=32&d=mm&r=gwefru

Projects Series 10

TEST YOUR SKILLS BRODLY

1 / 10

Q91. Which is generally not regarded as one of the three categories of culture that
managers should master?

2 / 10

92. Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8
and an SPI of 1.25. What is a plausible explanation for that?92

3 / 10

Q93. Some colleagues told you that they are planning, executing, monitoring and
controlling a project by use of milestones only with durations between 1 and 4
weeks. What do you think?93

4 / 10

Q94. Together with your team, you applied three-point estimation on a critical path
Q94.which consists of two activities.The following duration uncertainties are all calculated assuming a ±3sigma
confidence interval.The duration uncertainty—defined as pessimistic minus optimistic estimate—of
the first activity is 18 days; the second estimate has an uncertainty of 24 days.
Applying the PERT formula for paths (beta distribution), what is the duration
uncertainty of the entire path?

5 / 10

Q95. You are just leaving a meeting during which you have been assigned as the
manager of a project to build a sub-station that is part of a major electric power
distribution system. The decision to run the project has been made before your
assignment and without your involvement. Some basic decisions on deliverables,
staffing, budgeting and on the completion date have already been made as well.
What should you do first?

6 / 10

Q.96. A member of the project management team has come up with a 3D model of
stakeholder influence and interest in your project. What could this be referred
to?

7 / 10

Q97. Which is not a goal in both project management and quality management?

8 / 10

Q98. You created a baseline of your system configuration and added several changes
to that as amendments. Meanwhile you are afraid that the big number of Deltas
may cause inconsistencies and make you unable to understand the current
system configuration. What should you do?

9 / 10

Q99. A request, demand or assertion of a contract partner for consideration,
compensation or payment under a legally binding contract, such as a disputed
change, is often referred to as a____

10 / 10

Q100. Projects may be initiated by all of the following except____.